- A generating station has a maximum demand of 30 MW, a load factor of 60% and a plant capacity factor of 50%. The reserve capacity of the plant is
- A 100 km long transmission line is loaded at 110 kV. If the loss of the line is 15 MW and the load is 150 MVA, the resistance of the line is
(a) 8.06 ohms per phase
(b) 0.806 ohms per phase
(c) 0.0806 ohms per phase
(d) 80.6 ohms per phase
- When the load on a transmission line is equal to the surge impedance loading
(a) The receiving end voltage is less than the sending end voltage
(b) The sending end voltage is less than the receiving end voltage
(c) The receiving end voltage is more than the sending end voltage
(d) The receiving end voltage equal to the sending end voltage
- HVDC transmission is preferred to EHV AC because
(a) HVDC terminal equipments are inexpective
(b) VAR compensation is not required in HVDC systems
(c) System stability can be improved
(d) Harmonic problem is avoided
- Zero-sequence current is used for relaying purpose only in the case of
(a) Phase over current relay
(b) Phase impedance relay
(c) Ground over current relay
(d) Ground impedance relay
- In order to quench the are quickly and also optimize the dimensions generally
(a) Air blast C.B. is preferred
(b) Oil C.B. is preferred
(c) SF6 C.B. is preferred
(d) Minimum oil C.B. is preferred
- The corona loss in a 50 Hz system is 0.25 kW/ph/km. At a frequency of 60 Hz, the corona loss would be
(a) 0.30 kW/ph/km (b) 0.36 kW/ph/km
(c) 028 kW/ph/km (d) 0.21 kW/ph/km
- The critical point lies within the nyquist plot then the system is
(a) Marginally stable
(b) Unstable
(c) Stable
(d) Undetermined